Guston Chalkpit Solar Farm Construction Programme – September W4 Update

The current planning for the solar farm construction is that work relating to the DNO (Electricity company) substation will be undertaken first (with the DNO cable route operations now nearing completion).

Residents may therefore notice more activity around where the operational access is to be located.

Please be assured that this will not be the delivery entrance for the solar farm construction. It will relate specifically to the DNO substation requirement, and is being undertaken by the contractor undertaking DNO works.

The formation of the temporary construction access (on The Lane near Deal Road) for the main solar farm work will follow on from this.

This ensures that the work will be undertaken sequentially and with the least disruption.